CAAB
Dhaka Airport’s Third Terminal on track for completion this Oct, flights expected from early 2025
The construction of the third terminal at Hazrat Shahjalal International Airport in Dhaka is set to be completed by October this year, with flight operations expected to begin in early 2025, officials from the Civil Aviation Authority of Bangladesh (CAAB) have confirmed.
According to CAAB, the third terminal’s construction is in its final stages and is on track to be completed by the October deadline. The Civil Aviation Authority will take over the terminal from the contractor in October, following which the process of scheduling flights from the new terminal will commence early next year.
Following the fall of the Awami League government on August 5, uncertainty arose over the timely completion of the terminal. However, the interim government soon restored normalcy to the construction process.
The striking design of the third terminal building has drawn attention in the project area, with finishing touches underway both inside and outside the facility.
Read more: Target set for Dhaka Airport Third Terminal's full functionality by December 2024: CAAB Chairman
Air Vice Marshal Md Monjur Kabir Bhuiyan, Chairman of CAAB, recently inspected the progress of the third terminal. He directed the officials and workers involved in the project to ensure timely completion with a high standard of work.
“About 98% of the work on the third terminal has already been completed, and overall progress is satisfactory. I have instructed those involved to finish the remaining tasks promptly,” Air Vice Marshal Monjur told UNB. “We expect all work to be completed by October. After taking over the terminal from the contractor, we will prepare to launch flight operations.”
Consultancy firm Nippon Koei has estimated that around 6,000 skilled workers will be needed for the operation, maintenance, and security of the terminal, with nearly 4,000 of them required for security alone. However, CAAB officials said that it might take a few months to recruit the necessary workforce, meaning the terminal may not be fully operational immediately. Initially, CAAB and Biman Bangladesh Airlines will manage the terminal, with full operations likely to begin in February next year.
Once operational, the third terminal will increase Hazrat Shahjalal International Airport’s passenger handling capacity by an additional 12 million passengers annually. Currently, the airport’s first and second terminals manage between 120 to 130 flights of more than 30 airlines daily, serving around 20,000 passengers. This equates to a capacity of approximately 8 million passengers per year.
The new terminal will add 230,000 square meters of space to the airport, featuring 115 check-in counters, 66 departure and 59 arrival immigration desks, and three VIP immigration desks. It will also include 27 baggage screening machines, 40 security scanners, 12 boarding bridges, 16 carousels, and 11 body scanners.
The construction project, launched by the government in 2017, began on December 28, 2019, with an estimated cost of Tk 21,398 crore. The Japan International Cooperation Agency (JICA) is providing Tk 16,141 crore as a loan, with the remaining funds coming from the Bangladesh government. The construction is being carried out by Japan’s Mitsubishi and Fujita and South Korea’s Samsung.
CAAB officials noted that once completed, the terminal will accommodate 37 aircraft at a time and feature two high-speed taxiways to reduce waiting times on the runway. Two buildings have also been constructed for import and export cargo operations. A three-story parking facility for 1,350 vehicles is nearing completion. Initially, 12 out of the 26 boarding bridges will be operational, with 15 self-service check-in counters and 10 automated passport control counters available for departing passengers.
The terminal has been designed to ensure smooth entry and exit for passengers. It will be connected to the elevated expressway, and airport railway station via a tunnel. Hajj pilgrims will also have a dedicated tunnel from the Ashkona Hajj Camp to the third terminal.
Last year, on October 7, former Prime Minister Sheikh Hasina partially inaugurated the terminal as part of her government’s development efforts ahead of the national elections. At that time, the government had announced that flights would operate from the third terminal by October this year.
Read more: Govt will decide on ground handling at Dhaka airport’s third terminal and Biman is ready: CEO
3 months ago
Construction of Dhaka Airport’s Third Terminal set to be fully complete by April 5
In a significant development for Bangladesh’s aviation sector, the construction of the third terminal at Dhaka’s Hazrat Shahjalal International Airport (HSIA) is slated to be fully completed by April 5, 2024, with the terminal expected to be fully operational by October. This marks a pivotal moment in the expansion and modernization of the country’s aviation infrastructure.
The Civil Aviation Authority of Bangladesh (CAAB) will take over the terminal’s responsibilities from the contractor once the construction is completed. This transition will initiate the process of moving operations from the old terminals to the new one, focusing on Operational Readiness and Airport Transfer (ORAT) project.
AKM Maksudul Islam, the project director, told UNB that nearly all construction work, including civil engineering tasks, is nearing completion. Any remaining work is expected to be finalized in the first week of April, ensuring a smooth handover to CAAB by April 6. Preparations are underway to fully launch the terminal’s operations in October, including the completion of system integration and calibration tasks, which have successfully passed multiple evaluations.
Read more: Terminal 3 will transform Bangladesh's passenger and cargo handling capabilities: EU Ambassador
Air Vice Marshal M Mafidur Rahman, Chairman of CAAB, informed UNB that the third terminal is almost ready for flight operations and is expected to be fully functional by October. The completion of this terminal will significantly increase Dhaka airport’s capacity, facilitating the growth of domestic and international airlines’ operations. This expansion is anticipated to improve passenger amenities, increase revenue, and enhance the airport’s overall efficiency.
9 months ago
With promise to transform country’s aviation sector, Dhaka Airport’s Terminal 3 set for soft opening today
The much-anticipated third terminal of Hazrat Shahjalal International Airport, which promises to transform the face of the country’s aviation sector, is set to have its soft opening on Saturday morning (October 7).
Prime Minister Sheikh Hasina will officially inaugurate the new terminal for the country’s leading international airport, that stands out as one of the most talked-about and exciting among all the ‘megaprojects’ undertaken by the AL-led government.
Rehearsals are currently underway on-site in preparation for the inauguration program. Once the prime minister has completed the formalities, a special flight operated by state-owned Biman Bangladesh will depart from Dhaka using the newly constructed third terminal. Ground handling services for this special flight will be provided by the airline.
Target set for Dhaka Airport Third Terminal's full functionality by December 2024: CAAB Chairman
Preparations for the inauguration are being carried out collaboratively by the Biman Bangladesh Airlines Authority and the Civil Aviation Authority of Bangladesh (CAAB). A Biman flight, BG371 to Kathmandu, has already departed twice from the terminal to rehearse for the opening, although immigration and other paperwork was not done there.
Talking to UNB ahead of the inauguration, Air Vice Marshal M. Mafidur Rahman, chairman of CAAB, said that approximately 90 percent of the construction of Terminal 3 has been completed under the Shahjalal International Airport Expansion Project (Phase I).
Apart from the main terminal, the cargo complex comprising both export and import facilities, is nearly complete, said the CAAB chairman: “The cargo complex is in its final stages and is expected to be operational by March or April.”
HSIA Terminal 3: Final preparations on course for Oct 7 inauguration
Security arrangements for the airport have been meticulously planned for Saturday’s soft opening.
“Our target is to make the terminal fully functional for passengers by December 2024. The work is progressing ahead of schedule, and we are confident that the terminal will be operational before the planned deadline,” he said.
Meanwhile Md. Shafiul Azim, managing director of Biman Bangladesh, told UNB the national flag carrier is fully prepared for the soft opening of Terminal 3.
“New equipment has been procured for the ground handling of Terminal-3, and international standard uniforms have been provided to the staff on duty. The airline conducted exercises, including ground handling, in preparation for the inauguration,” he said.
Terminal 3 is expected to provide a sea-change in terms of passenger experience and choice in a state-of-the-art setting. It starts with the 37 aircraft parking spaces, which has already seen some airlines that never flew to Bangladesh before, make queries to include Dhaka as a destination in the near future.
Soft opening of Dhaka airport’s 3rd terminal on Oct 7: CAAB Chief
The 26 boarding bridges (of which 12 are to be launched in October), along with 115 check-in counters, including 15 self-service, promise a breezier experience for anyone departing Dhaka, or flying in. .
The baggage handling system will be on the ground floor, departure lounge and boarding bridge on the second floor, and extensive duty-free shops and exit lounges.
Terminal 3 will have the capacity to serve 1.20 crore (12 million) passengers annually on its own, once fully operational. At present the airport is able to serve 80 lakh (8 million) passengers in a year. A multi-storey car parking facility, customs hall, VIP and VVIP passenger areas, and a transit passenger lounge are also part of the terminal's offerings.
The three-storey terminal, designed by Rohani Baharin of internationally renowned CPG Corporation (Private) Limited Singapore, will have a floor space of 230,000 square metres. Baharin’s CV includes the acclaimed third terminal of Singapore’s Changi Airport, as well as Ahmedabad’s new international airport.
The second phase of the project will involve constructing a corridor and the multi-level car parking building with 1,350 parking spaces.
In terms of passenger convenience, the new terminal will introduce automated passport control or e-gates, reducing wait times. Passengers can choose self-immigration through the e-gates or opt for assistance at one of 56 exit immigration counters. A modern fire-fighting system and advanced security screening process will enhance safety measures.
Read more: Groundhandling contract for Terminal 3 will go to Japan: CAAB chairman
The terminal will also include movie lounges, food courts, airline lounges, and world class duty-free shops. Facilities like Wi-Fi, mobile charging, prayer areas, and a Meeters and Greeters Plaza are thrown in for good measure.
Additionally, special arrangements have been made for mothers, including breastfeeding booths, diaper-changing areas, and a family bathroom. Children will have a dedicated play area.
The project, originally with an estimated cost of Tk 13,610.47 crore, got the nod of the Executive Committee of the National Economic Council (ECNEC) in October, 2017. However, the cost rose substantially later on as the entire vision changed and it was decided to go for a world class facility with the potential to transform the aviation sector in the long term. The final cost approved for the project stands at Tk 21,400 crore.
JICA, the Japanese government’s international development agency, has been helming the project as the main financier, with a consortium of three leading international firms - Mitsubishi, Samsung C & T (the construction arm of Samsung) and Fujita JV - contracted to implement it. It marked the first and till now only project in Bangladesh for Samsung C & T, the firm behind such international landmarks as the Burj Khalifa, Taipei 101, and the Petronas Towers, among others.
Read more: Govt will decide on ground handling at Dhaka airport’s third terminal and Biman is ready: CEO
1 year ago
Four private airlines, inc. three that are closed, owe CAAB over Tk 1223cr
The Civil Aviation Authority, Bangladesh (CAAB) is owed Tk 1223 crore by four private airlines.
Out of these four airlines, three are currently closed. The amount the three closed airlines owe is over Tk 1192 crore.
This information was divulged in the meeting of the Parliamentary Standing Committee on Ministry of Civil Aviation and Tourism on Sunday (September 17, 2023) held at the Sangsad Bhaban.
Also read: Irregularities in leasing Egypt Air planes: ACC questions 7 CAAB officials
The Parliamentary Committee on Ministry of Civil Aviation and Tourism wanted to know how much money CAAB owes or is owed in their dealings with domestic private airlines companies.
CAAB gave a report in this regard in the parliamentary standing committee meeting today with its chairman RAM Obaidul Muktadir Chowdhury in the chair.
According to the sources, CAAB in its report said that it is owed a total of Tk 1,222.98 crore by Regent Airways, Novo Air, United Airways and GMG Airlines. Among them, only Novo Air still flies.
As of last May, two other private airlines, US Bangla and Air Astra, both of which are still in business, have no debt.
Also read: Civil Aviation Ministry asked to take action against CAAB officials for irregularities
CAAB is owed more than Tk 408 crore by Regent Airways, while GMG Airlines owes more than Tk 396 crore.
CAAB is owed Tk 388.97 crore by United Airways and from Novo Air it is owed Tk 29.48crore.
After the meeting, a press release of the Parliament Secretariat informed that the parliamentary committee has recommended taking necessary measures to collect the money owed by the private airlines.
Meanwhile, the report of the sub-committee on the investigation of the Hotel Intercontinental renovation project which was presented in the previous meeting of the committee was in the discussion list of today’s meeting.
The report claimed that it was not needed to spend exorbitantly on the renovation works.
Also read: ACC finds 19 areas of corruption in Biman, Caab
Government money has been unnecessarily spent for the benefit of certain people, the report said.
According to the report, the rooms of 26 square meters has been increased to 40 square meters. As a result, the number of rooms was reduced to 226 from 272. The report claims that this was not necessary.
Apart from this, the committee recommended to widen the road from Cox's Bazar airport to the city on an urgent basis and improve its beauty, maintain the cleanliness of the beach and implement the activities with mutual coordination.
The committee members Mosharraf Hossain, Ashek Ullah, Syeda Rubina Akhtar, Kaniz Fatema Ahmed were present in the meeting.
1 year ago
HSIA Terminal 3: Final preparations on course for Oct 7 inauguration
Preparations are underway for the inauguration of the third terminal of Hazrat Shahjalal International Airport, or Terminal 3 - one of the most exciting and potentially transformative projects undertaken by the Awami League-led governments across three electoral cycles.
Prime Minister Sheikh Hasina will inaugurate the first phase of the project on October 7.
However, the full utilisation of the terminal by passengers is expected at the end of 2024. This is due to the necessary calibration and preparation of the equipment used in terminal operations, which is projected to take up most of 2024.
The chairman of the Civil Aviation Authority of Bangladesh (CAAB), Air Vice Marshal Mafidur Rahman,confirmed to UNB that Prime Minister Sheikh Hasina will officially open the terminal with the usual fanfare associated with the inauguration of megaprojects under the present dispensation, on October 7.
Govt will decide on ground handling at Dhaka airport’s third terminal and Biman is ready: CEO
“The preparation for the inauguration is in its final stages. Structure of the terminal is ready, and now equipment is being installed,” said AVM Mofidur.
He further stated that airlines will be able to use the new parking apron and taxiway . The old terminal's apron can accommodate 29 aircraft, but after the soft opening, the third terminal's apron will be able to accommodate an additional 8 to 10 aircraft.
What sets Terminal 3 apart
The CAAB chairman said 37 aircraft can be parked at a time once the terminal – with an area of 5,42,000 square meters – is fully opened.
There will be 26 boarding bridges. Of these, 12 boarding bridges will be opened in October. There will be a total of 115 check-in counters (including 15 self-service check-in counters) for exits, according to CAAB.
In addition, there will be 10 self-service passport control counters for immigration, along with 66 external immigration counters. For arriving passengers, there will be 5 self-service check-in counters, making a total of 59 counters.
Currently, the existing terminal has 8 baggage belts, while the Third Terminal will have 16 baggage belts for arriving passengers. There will be separate belts for oversized luggage.
Soft opening of Dhaka airport’s 3rd terminal on Oct 7: CAAB Chief
The chairman mentioned that a multilevel car parking building with 1,350 parking spaces will be constructed for car parking at Terminal 3.
Below the new terminal, there will be a baggage handling system, and on the second floor, there will be an arrival lounge, a cantina, and boarding bridges, according to CAAB. Additionally, there will be a Duty-Free shop and an arrival lounge nearby.
The total area of the third terminal building is going to be 230,000 square metres, with a capacity of handling 12 million passengers annually.
The baggage handling area is 54,000 square metres, and the fire-fighting station with equipment covers 4,000 square metres. The import cargo terminal is 27,000 square metres, and the export cargo terminal is 36,000 square metres. The connecting taxiway is 66,500 square metres.
12 boarding bridges will be operational when Dhaka Airport’s 3rd Terminal partially opens this Oct: CAAB
There are two rapid exit taxiways, covering 41,500 square metres. Furthermore, the airport will have associated road connections, an elevated expressway, and the necessary equipment (automated warehouses) for passenger and cargo handling. All these activities are currently underway.
Additionally, there will be a hall and six channels for customs for passengers arriving from other countries. VIP services have been arranged for VIP passengers.
In the southern part of the Third Terminal, there is a 3,650-square-metre area dedicated to VIP and VIP passenger services.
A large lounge has been constructed for transit passengers in the new terminal. It will serve 40,00,000 passengers annually. However, there will be no direct connection with the old two terminals for now. A corridor will be constructed in the second phase of the project.
According to the CAAB chairman, 120–130 aircraft from over 30 airlines takeoff and land at Hazrat Shahjalal International Airport's first and second terminals every day.
About 20,000 passengers use the airport's two terminals every day. As a result, the HSIA currently has the capacity to serve about 80 lakh passengers annually.
Fakhrul returns from Singapore, complains of harassment at airport
With the opening of the third terminal, it will be possible to serve another 12 million passengers, he said. Once Terminal 3 , passengers will be able to avail the following facilities:
Self-immigration facilities
The new terminal building will feature a total of 10 automatic passport control stations or e-gates at the departure area. This innovative system allows passengers to complete the immigration process independently, eliminating the need to interact with immigration authorities.
Nevertheless, for those passengers who prefer not to handle immigration procedures independently, there will be 56 exit immigration counters staffed by immigration officials ready to assist them. Additionally, there will be 5 e-gates available for passengers arriving in Bangladesh from other countries, and 54 arrival immigration counters to ensure a smooth entry process.
State-of-the-art scanning systems for security
Currently, passengers undergo manual security checks at Hazrat Shahjalal International Airport. However, this practice is set to change. In the future, security checks will be entirely automated, eliminating the need for physical contact during the screening process right up until the passengers aboard the plane.
As a part of this streamlined procedure, passengers will be required to raise both hands inside the body scanner machine. This advancement is expected to result in significant time savings for both passengers and airport security personnel.
Less commuting hassles for passengers
Once the terminal officially opens, passengers will experience seamless travel transitions to and from the airport. This is attributed to the on-going construction of underground tunnels and flyovers in conjunction with the third terminal building, which will significantly enhance travel convenience.
Passengers will have effortless access to ground transportation, including convenient connections to the metro rail and Dhaka Elevated Expressway, facilitating swift departures and arrivals. Moreover, the terminal will be equipped with a state-of-the-art international-quality firefighting system to ensure passenger safety.
GP customers to enjoy roaming services at Dhaka airport
Other facilities include:
To cater to passengers' needs during transit, a range of amenities is being introduced. These include movie lounges and food courts designed to enhance the passenger experience. Additionally, airline lounges and dayrooms will be available for travellers seeking comfort and relaxation. Furthermore, 14 duty-free shops will be strategically placed throughout the terminal, offering passengers opportunities for both leisurely strolls and shopping.
Passengers can expect to find an array of amenities such as food courts, food galleries, Wi-Fi connectivity, and mobile charging facilities, both within and outside the terminal. To accommodate passengers' religious needs, separate prayer areas will be designated for men and women. The new terminal will also feature a dedicated "meeters and greeters plaza" to facilitate the welcoming of visitors.
The lounge will provide a dedicated breastfeeding booth, diaper-changing facilities, and a spacious family bathroom.
Additionally, a children's play area equipped with sleeper swings will be available for young travellers to enjoy.
Passengers at the new terminal will have access to 24-hour medical care, including health inspection services staffed by doctors, first-aid rooms for immediate medical assistance, testing centres, and isolation areas for various diseases, including COVID-19.
Back in 2017, the government initiated the Terminal 3 project for Dhaka’s main airport. However, work on the construction of the terminal commenced on December 28, 2019.
This ambitious and visionary project has been estimated to cost approximately Tk 21,398 crore. Notably, the Japan International Cooperation Agency, or JICA, is providing Tk 16,141 crore in the form of a loan to support the project, while the Government of Bangladesh is coughing up the remaining Tk 5,257 crore.
The highly coveted contract for construction of HSIA Terminal 3 was won by a consortium made up of 3 of Asia’s leading firms in the sector: Japan's Mitsubishi Heavy Industries, as well as Fujita Corporation, and South Korean behemoth Samsung C&T Corporation ("Construction & Trading Corporation”).
Where was the CCTV camera? Investigators wonder about missing gold at Dhaka Airport customs
1 year ago
Soft opening of Dhaka airport’s 3rd terminal on Oct 7: CAAB Chief
Hazrat Shahjalal International Airport’s third terminal will have its soft opening on October 7. Prime Minister Sheikh Hasina will inaugurate the new terminal.
Air Vice Marshal Muhammad Mafidur Rahman, chairman of Civil Aviation Authority of Bangladesh (CAAB), said this during a press conference on Tuesday (August 08, 2023) noon at the under-construction third terminal.
Read: 12 boarding bridges will be operational when Dhaka Airport’s 3rd Terminal partially opens this Oct: CAAB
“We were informed yesterday (August 7) by the Prime Minister’s office (PMO) that the premier will inaugurate the third terminal at a soft opening on October 7,” the CAAB chief said.
However, he said, passengers will be able to fully use the third terminal by the end of 2024.
Read: Groundhandling contract for Terminal 3 will go to Japan: CAAB chairman
“We want to complete 90 percent of the third terminal project before October 7, and we are optimistic that the work will be finished ahead of schedule,” added the CAAB chairman.
1 year ago
12 boarding bridges will be operational when Dhaka Airport’s 3rd Terminal partially opens this Oct: CAAB
The third terminal of Dhaka’s Hazrat Shahjalal International Airport will be partially opened by October this year, and it is set to be fully operational next year, Civil Aviation Authority of Bangladesh (CAAB) Chairman Air Vice Marshal Muhammad Mafidur Rahman told UNB on Sunday (August 06, 2023).
The construction of the terminal is currently in its final stage and over 85 percent work has been completed, he said.
Once fully operational, the new Dhaka airport terminal, covering an area of 5,42,000 square metres, will be capable of serving more than one crore passengers annually, the CAAB chairman added. State of the art amenities will also be offered to passengers.
Read: Groundhandling contract for Terminal 3 will go to Japan: CAAB chairman
“As construction is in its final stage, the magnificent architecture of the third terminal building is now visible. Currently, work on interior decoration and installation of various types of equipment is going on,” the CAAB chief informed UNB.
2 CRORE PASSENGERS WILL BE ABLE TO USE DHAKA AIRPORT EVERY YEAR
The CAAB chairman said that currently 120-130 planes of over 30 airlines take off from and land at Hazrat Shahjalal International Airport’s Terminal 1 and Terminal 2.
“Every day about 20,000 passengers use the two terminals of the airport. As such, Dhaka airport serves around 80 lakh (8 million) passengers annually. It will be possible to serve an additional 1.2 crore passengers when the third terminal is opened,” he said.
1 year ago
All 8 airports to get facelift with state-of-the-art amenities by this year: CAAB Chief
Civil Aviation Authority of Bangladesh (CAAB) Chairman Air Vice Marshal M Mafidur Rahman has said that the expansion and modernization works of all 8 airports – international and domestic – in the country, involving Tk 35,850 crore, will be completed by the end of the current year.
“Once the work is completed, there will be major changes in infrastructures of the airports. All the airports will be equipped with modern amenities, and they will get an attractive look,” the CAAB chief told UNB in an exclusive interview recently.
Work is going on in full swing to implement the projects as per the instructions of Prime Minister Sheikh Hasina, he said, adding that the engineers of CAAB worked round the clock even during the Covid-19 pandemic.
“We have ensured the quality of the work and maintained European standard in terms of equipment and safety materials,” he added.
“More than 70 percent work of the third terminal of Hazrat Shahjalal International Airport in Dhaka has been completed and the operational activities of the new terminal will be inaugurated in October this year. Prime Minister Sheikh Hasina will inaugurate the third terminal,” he said.
Read more: Domestic airports are getting face-lift to offer quality services to passengers: CAAB
“After completion of the third terminal, passenger handling capacity at Dhaka airport will increase from 10 million to 22 million. Besides, cargo handling capacity will rise from 2.20 lakh ton to 7 lakh ton,” the CAAB chairman added.
He said that passengers will be able to avail international standard services once the third terminal opens.
Construction work of 73,548 square meter cargo apron of Hazrat Shahjalal International Airport is now underway.
Eighty-five percent of the project has been completed and after implementation, the apron will be able to park additional 4 long-range cargo aircraft.
Read more: World-class third terminal of Dhaka Airport to be visible by Dec: CAAB
Besides, the construction of general aviation hangar, hangar apron and fire station expansion project at Dhaka airport, at a cost of Tk 430 crore, is on.
1 year ago
CAAB trolleyman held with Tk32 lakh gold at Chattogram airport
A trolleyman of the Civil Aviation Authority of Bangladesh (CAAB) was detained with four gold bars worth Tk32 lakh at Shah Amanat International Airport in Chattogram Saturday, authorities said.
The detainee was identified as Md Ismail of Hathazari upazila.
Read: Man held with Tk. 1.8 crore worth gold
On information, Ismail was held at the parking area of the airport around 10:30am, Wing Commander M Farhad Hossain Khan, director of Shah Amanat Airport, said.
The gold bars were seized from the bags he was carrying on his trolley, he added. "Legal actions will be taken against Ismail."
2 years ago
Improvement in services can play vital role to turn Bangladesh into regional aviation hub: Speakers
Speakers at seminar on ‘Prospect of Bangladesh as Regional Aviation Hub’ have suggested the government to improve the services at the country’s domestic and international airports.They said only improvement in aviation services could attract the foreign tourists that would play vital role to turn Bangladesh into a regional aviation hub.Civil Aviation Authority of Bangladesh (CAAB) Air Vice Marshall M. Mafidur Rahman, presiding over the function, said after completion of the construction of third terminal of the Shah Jalal International Airport, aviation passengers will see a substantial improvement in the services.“We will maintain international standard in our service… We’ve already appointed foreign consultants in this regard’, he told the seminar, held on the sideline of the international travel and tourism fair titled : Triplover Dhaka Travel Mart-2022, at the Pan Pacific Sonargaon Hotel in the city.
Also read: Bangladesh to be turned into a global aviation hub: Hasina
Organised by The Bangladesh Monitor the seminar was also addressed by Md. Abdullah Al Mamun, Managing Director of US-Bangla Airlines; Mofizur Rahman, Managing Director of Novoair; and A T M Nazrul Islam, Managing Director of United Airways Bangladesh Ltd.Representatives from different stakeholders of the country’s aviation industry including regulators, airlines, concerned apex trade bodies, aviation experts, and aviation reporters also spoke on the occasion.The participants mainly discussed on the existing hurdles and opportunities in development of Bangladesh aviation sector, and how to harness the potentials in establishing Bangladesh as a regional aviation hub, in line with the aspiration of the nation.
Also read: Aviation sector growth to triple in next 15 years: State Minister
Kazi Wahidul Alam, Editor The Bangladesh Monitor, moderated the session.
2 years ago