Three officials and employees of Bangladesh Petroleum Exploration and Production Company (Bapex) suffered burn injuries in a sudden gas explosion while conducting a land survey at a deep tube well in Inani of Ukhiya upazila in Cox's Bazar on Sunday.
The incident occurred around 1:00pm at Chhoto Inani Khal Bridge area in Jaliapalong union, when a sudden burst of flames emerged from a gas diversion line.
The injured were identified as Bapex Deputy General Manager (DGM) Rakibul Hasan, Firoz Ahmed and Mohammad Joni.
They were admitted to Cox's Bazar District Sadar Hospital for treatment.
Dolon Acharya, in-charge of Cox's Bazar Fire Service and Civil Defence station, said three Bapex officials and employees were injured in an explosion during geological survey work.
Bapex Project Manager Anisur Rahman said technical and survey activities had been underway at the site after the fire was brought under control on November 27.
As part of the ongoing work, flames suddenly burst out through the gas diversion line on Sunday, burning the three workers, he said.
However, their conditions were not critical, he added.
Four more employees were also injured during the incident and they were given first aid, said Project Manager Anisur Rahman.
Earlier, on October 27, gas suddenly started escaping from a deep well during drilling operations near Chhoto Khal Bridge in Inani.
The blaze continued for 31 days before a Bapex expert team brought it under control on November 27 using locally developed technology.
To control the fire, the team installed a 30-inch-diameter casing pipe around the well, arranged gas discharge through a diversion line and applied several technical measures.
Bapex said that although the surface fire had been brought under control, further technical work was still underway to reduce gas pressure to a safe level and prepare for the next phase of exploration.
The latest accident occurred during these ongoing operations, the company said.
Following the incident, engineers and workers continued operations at the site with enhanced safety measures.
Bapex claimed that the situation was currently under control and that all necessary measures were being taken to make the well completely safe.