The U-Turns are being constructed on the Satrasta (Tejgaon)-Uttara House Building street at a cost of Tk 31.81 crore.
Also read: U-loop projects to be finished by Dec 31: DNCC Mayor
The three U-Turns opened Sunday are at Tejgaon BG Press point, Nabisco/Kohinur Intersection and Banani Chairman Bari point, said a DNCC handout.
DNCC Mayor Atiqul Islam said traffic congestion will be eased and travel time will be saved further thanks to the three U-turns.
Also read: Flyovers in Dhaka: Are they any solution to traffic gridlock or scraps?
When all the U-turns will be in operation, the sufferings of the city’s commuters will be reduced to some extent, said the mayor.
With the newly-opened ones, six have so far been made operational on the city’s streets.
Also read: Decentralisation to help ease Dhaka's traffic gridlock: Mannan
The three U-Turns opened earlier are at Kaula Flying Academy point, Uttara Rab-1 office point and Uttara Jashim Uddin Intersection.
The construction of four other U-Turns is in progress at Mohakhali Inter-district Bus Terminal point, under the Mohakhali Flyover, Banani-Kakoli railway station point and under Banani Flyover.
Also read: Dhaka returns to old face amid rising rate of COVID-19 infection
The plan for construction of the remaining U-Turn adjacent to Army Golf Club was dropped during the revision of the project.
The cost estimated at the original project was Tk 24.83 crore, which was increased by Tk 31.81 crore during revision.