The work on the construction of Rooppur Nuclear Power Plant (NPP) is going on in full swing as the installation of the dome of outer containment at the reactor building of Unit-1 has begun to upgrade safety features protecting any serious external shocks.
It will enhance the safety features of the country’s first nuclear power plant.
According to Rosatom, the Russian contractor of the Rooppur NPP, the installation of the lower tier of the dome has already been completed as part of the work.
Read more: Rooppur Nuclear Power Plant to get powerful reactors: Rosatom DG
It took five hours for installing the heavy structure with a weight of 200 tonnes and a diameter of 46.3 meters in the design position at a height of 48.8 metres. Installation of the upper tier and concreting will take place in the coming days.