The final phase of the six-lane expansion work of the Dhaka-Narayanganj Link Road has been stalled for a long time.
The construction from Signboard to Chandmari on the road was completed almost a year ago, but the work on nearly one kilometer of the road from Chandmari to Chashara is still unfinished, causing severe inconvenience to commuters.
This road has become one of the main reasons for the persistent traffic jams in Narayanganj city. Vehicles can travel smoothly between Signboard and Chandmari without much hindrance, but they have to wait for a long time at the entrance. Similarly, vehicles traveling from Chashara to Signboard also have to wait for extended periods at the beginning. Moreover, there are large potholes across the road, leading to frequent accidents.
Dense fog may disrupt flight, vessel operation, road communication: BMD
According to sources from the Roads and Highways Department (RHD), the road from Chashara to Signboard is 8.15 kilometers long. It connects Narayanganj city to the Dhaka-Chittagong and Dhaka-Sylhet highways. To upgrade this important road to the proper standard, the Road Transport and Highways Division drafted a Detailed Project Proposal (DPP) and sent it to the Planning Commission. After receiving the project proposal, the Project Evaluation Committee (PEC) meeting was held on July 8, 2019.
Based on the recommendations made in that meeting, the DPP was revised. The proposal was then presented to the Executive Committee of the National Economic Council (ECNEC), where it was approved. On December 9, 2020, the purchase proposal for the six-lane upgrade project was approved.
The approved project for upgrading the Dhaka-Narayanganj Link Road (R-111) to six lanes has an estimated cost of Tk 364 crore 25 lakh 65 thousand. On February 9, 2021, a contract was signed between the Roads and Highways Department and the contracting company for the project, which was supposed to be completed by June 2022. However, the deadline was extended until June 2023, and the project cost was increased to Tk 489 crore.
Indefinite strike on bus services on Sylhet-Zakiganj road called off
Despite the extended time, the construction work has not been completed, and the deadline was further extended by another year until June 2024. However, the work remains unfinished, and there is no certainty on when it will be completed.
After August 5, 2024, following the ouster of the Awami League government, the work came to a complete halt. There is no information of when it will resume.
Shahana Ferdous, Executive Engineer of Narayanganj Roads and Highways Department, said, "The delay in work is due to some structures in the Chandmari area that could not be removed and the Narayanganj Rifles Club at the city entrance. However, this issue has now been resolved, and work will begin soon. The entire project will be completed before June 2025."