Meanwhile, City Mayor Ariful Haque Chowdhury visited the work to remove the pillars and wires on Sunday morning while Councillor of Ward-1 Syed Towkiul Hadi, Sylhet Chamber of Commerce and Industry President Abu Taher Md Shoyeb, and Sylhet Power Department officials were present.
Mayor Ariful said that for the first time in the country, underground electricity transmission project has been launched successfully where electric lines are installed under-ground just like in developed countries.
“The charm of the city bloomed as lumber of wires and electric pillars have been removed from the roadsides,” the mayor said.
Initially, the power supply would operate from Shahjalal mazar area to city’s Court point area, Ariful stated, and later the system would be implemented in all other areas of the City Corporation sequentially, the Mayor added.
Councillor Syed Tawfikul Hadi said Sylhet has stepped ahead towards building a digital city, and that a dream has taken shape in reality. He thanked the government for this project.
President of Sylhet Chamber of Commerce and Industry Abu Taher Md Shoyeb said: “We’re happy that the project took place in Sylhet first.”
SCC Chief Engineer Md Nur Azizur Rahman said it was a challenging work that has been completed swiftly by the PDB and with the help of SCC.
The PDB should keep its persistent monitoring to ensure the power supply is uninterrupted, he insisted, adding that SCC would continue its cooperation in this regard.
Under the Tk 55 crore project, 11 KV 25 kilometer, 0.4 KV 18 kilometer and 33 KV two-kilometer underground electric transmission lines would be established.
A line would run from electric sub-station center via Amborkhana to Chowhatta while another from Chowhatta via Zindabazar- Court point to Sylhet Circuit House. The third one will stretch from Chowhatta to Osmani Medical College and Hospital.